Construction

Guru Peedam Roof Replacement Begins

The roofing company has begun replacing the roof of the Guru Peedam hall. The old concrete monier tile was there for more than 50 years, bearing many a rainfall and intense tropical sun before gradually starting to leak. The team finished removing one side of the tiles yesterday and will finish the other side today. A number of rafters will be replaced in the coming days before laying down the same roofing material as we did with Kadavul Temple.

Guru Peedam Roof Replacement Begins Read More »

Preparing for Guru Peedam Roof Replacement

In a couple weeks a contractor will come and replace the aged monier roof tiles of the Guru Peedam room with composite roof shingles. The wood A-frame ceiling rafters inside the room also have termite damage, so multiple rafters will be replaced at the same time. Here are Vishvanathaswami and Arinien starting to mill some of our redwood for this project.

Preparing for Guru Peedam Roof Replacement Read More »

Iraivan Temple Circumambulation Road Completed

The road construction is complete! Two sections were added to tie it to the road coming down from the main Aadheenam buildings. Drainage pipes were also installed underneath in strategic locations. The concrete contractor team did a great job and persevered despite the challenge of persistent rain on one day. For their good work, they were given a bonus and a case of noni juice, for which they were very thankful.

Within a few months, a second team will begin installing quartzite tile on top of the concrete.

Iraivan Temple Circumambulation Road Completed Read More »

Road Around Iraivan Temple Progressing Well

The contractor team is close to two thirds done with building the eight-food-wide road around Iraivan Temple. They started at the front entrance with the apron connecting hillside steps to the granite staircase, and have since been working their way around both sides of the temple at once. Three concrete trucks came a couple days ago, four yesterday, two more tomorrow, and some more will come several days after that.

Road Around Iraivan Temple Progressing Well Read More »

Iraivan Temple Road Day One, & Chitra Puja

A contractor team has arrived to begin two to three weeks of work to create a concrete road around Iraivan Temple, replacing the temporary crushed asphalt we have there now. Some time after they are done, another team will cover the road with quartzite tile. Besides allowing vehicles to conveniently drive around, the road can serve as a circumambulation path for pilgrims doing sadhana, and occasional parades.

Today the main focus was to dig out the area that will connect the stairs coming up the hill to the temple granite staircase, where more technical precision is needed to ensure that the eventual quartzite tile layer will be at just the right height next to the first granite stair. They will pour this area on its own first, then the rest of the road later.

Auspiciously, today also happened to be the monthly Gurudeva Chitra pada puja.

Also, we continue to have a flock of nene geese moving about the property.

Iraivan Temple Road Day One, & Chitra Puja Read More »

Kitchen Island Cabinetry Replaced

After many years of heavy use, the cabinets and drawers under our kitchen island counter were showing the signs of wear and tear, and termites had moved in. It was time to replace it. Longtime devotee and carpenter Kanda Alahan, from California, was kind enough to build a new set at home. He pre-assembled it, then disassembled and packed efficiently in a crate for shipping by sea, then reassembled it here. Our hired cook, Mani, took a couple days off while Kanda, along with multiple monks and our employee Doug, went about demolishing the old, cleaning the underside of the countertop for reuse and installing the new. It all went very smoothly and they were finished sooner than expected. Thank you Kanda!

Kitchen Island Cabinetry Replaced Read More »

Scroll to Top